Infrastructure:

  Work status during the Month of April, 2017.
Facility Category of Construction Status of All work
Target since inception  Achieved  In progress /taken up Not yet started Yet to be assigned
 Sub-centre  Construction of new Health Sub-centres
 
278 275 2 1 0
Construction of new Health Subcentre in AMC 16 16 0 0 0
Construction of new SC for building less SC 112 90 20 2 0
Up gradation of Health Sub-centre to IPHS  50 50 0 0 0
Minor Repair of SC  20 20 0 0 0
PHC Construction of new PHC  21 13 4 4 0
New building at existing PHC  7 6 1 0 0
New building at existing PHC without Quarter 9 0 9 0 0
Up gradation of PHC to IPHS
 
27 19 3 5 0
Up gradation of PHC to SDH as FRU  1 1 0 0 0
Up gradation of PHC to CHC  9 8 1 0 0
Renovation  (24x7 Service) of PHC  43 43 0 0 0
Renovation   of PHC  5 4 1 0 0
CHC Construction of new CHC  1 0 1 0  
Construction of new building in existing CHC  2 0 0 2  
Up gradation of  CHC to SDH 2 0 0 2 0
Up gradation of  CHC to IPHS  10 9 1 0 0
SDH Upgradation of SDH for FRU
 
7 6 0 1 0
Renovation of SDH  8 8 0 0 0
DH Up gradation of Dis. Hospital  2 2 0 0 0
Other activities Construction of State Institute of H&FW  1 1 0 0 0
Construction of MCH wing 1 0 0 1  
Construction of Warehouse  2 1 1 0 0
Up-gradation of
ANM Training Institute 
2 2 0 0 0
Neo-natal Care Unit (NCU) in DH / SH 2 2 0 0 0
Neo-natal Intensive care unit (NICU) in SDH  4 4 0 0 0
NBSU in SDH /CHC 9 8 0 1 0
DEIC in DH/SDH 3 3 0 0 0
Total 654 591 44 19 0