  Work status during the year 2020-21 (4th Quarter- Jan,2021 to March,2021)
Facility Category of Construction Status of All work
Target since inception 
Achieved 
In progress /taken up
Not yet started
 Sub-centre  Construction of new Health Sub - centres
 
277 277 0 0
Construction of new Health Subcentre in AMC 16 16 0 0
Construction of new SC for building less SC 110 107 3 0
Up gradation of Health Sub-centre to IPHS  50 50 0 0
Minor Repair of SC  20 20 0 0
PHC Construction of new PHC  21 20 1 0
New building at existing PHC  15 7 8 0
New building at existing PHC without Quarter 15 10 5 0
Up gradation of PHC to IPHS
 
33 27 6 0
Up gradation of PHC to SDH as FRU  1 0 1 0
Up gradation of PHC to CHC  9 9 0 0
Renovation  (24x7 Service) of PHC  43 43 0 0
Renovation   of PHC  4 4 0 0
CHC Construction of new CHC  1 0 1 0
Construction of new building in existing CHC  3 0 3 0
Up gradation of  CHC to SDH 2 0 2 0
Up gradation of  CHC to IPHS  14 10 4 0
SDH Upgradation of SDH for FRU
 
6 6 0 0
Renovation of SDH  8 8 0 0
DH Up gradation of Dis. Hospital  2 2 0 0
Other activities Construction of State Institute of H&FW  1 1 0 0
Construction of MCH wing 3 0 3 0
Construction of Warehouse  2 2 0 0
Up-gradation of
ANM Training Institute 
2 2 0 0
Neo-natal Care Unit (NCU) in DH / SH
2 2 0 0
Neo-natal Intensive care unit (NICU) in SDH
4 4 0 0
NBSU in SDH /CHC
9 9 0 0
DEIC in DH/SDH
3 3 0 0
Total 676 640 36 0


.



.